Project Management

Green Is Not a Status

A status color is a judgment someone made. Three questions that show what a green status leaves out.

By Joary Khairudin-Casey, Founder · Principal Consultant · July 20, 2026 · Quick Read · 4 min

Every status report I have ever seen has a color on it: green, yellow, or red. The color is supposed to tell you how the work is going. In my experience it often shows how confident the person filling it out felt when they picked it.

Status Colors

Green is a decision a person made. Someone looked at the schedule, the budget, and the open risks and decided the whole picture was fine.

I have watched a program stay green for four straight months and then turn red in a single week. Nothing dramatic happened that week. The program had been yellow the whole time. Everyone reporting to leadership kept choosing green.

The Green Test

So I started treating green as a claim I have to test. When a contractor or a team tells me a project is green, I ask three things.

First, green against what baseline? A project is on track against a specific schedule, budget, and set of deliverables someone agreed to. If the person cannot tell me the baseline, the color means nothing.

Then, what would have to be true next month for this to stay green? If staying green depends on a hire that has not happened, an approval that has not come through, or a risk that is still open, the project is yellow.

Last, what did you almost mark this? When someone says they almost went yellow, I treat the project as yellow.

My Pipeline

I use the same three questions on my business every week.

When I look at my pipeline, my first instinct is to call it healthy because I am busy. If my revenue goal for the year needs a certain number of signed engagements by a certain month, then “I have a lot going on” describes how I feel about the work. The honest status is the number of things closed measured against the number I said I needed by now.

The month I started scoring my work the way I score a contractor’s, I caught two problems in my pipeline while they were still yellow and early enough to fix them.

The Next Status Report

When you see a green status, it helps to ask what it is green against, what has to happen next month for it to stay green, and what the person almost marked it.

What on your status report is green right now that you have not tested since the last time someone told you it was fine?